Renovating your kitchen is one of the most exciting—and involved—home improvement projects you can undertake. Whether you’re dreaming of a sleek modern layout or a cozy farmhouse design, understanding the timeline is key to keeping your project on track and stress-free. At Echelon Builds, we’ve broken down the typical kitchen renovation timeline and included planning tips to help homeowners in Calgary prepare confidently.
Average Kitchen Renovation Timeline
A standard kitchen renovation can take 6 to 12 weeks once construction begins, but the full process—including planning and design—often spans 3 to 6 months. Here’s a general breakdown:
Planning and Design (2–6 weeks)
This is the most critical stage. It involves:
- Consulting with a contractor or designer
- Creating floor plans
- Choosing materials, finishes, appliances, and cabinetry
- Securing permits (if required)
Tip: Finalize design details and materials before construction begins to avoid delays later.
Ordering Materials (2–8 weeks)
Lead times vary depending on the materials chosen:
- Custom cabinets: 6–10 weeks
- Countertops (e.g., quartz or granite): 1–3 weeks after cabinet installation
- Appliances: 2–6 weeks
Tip: Order all major components early to keep construction moving on schedule.
Demolition (2–5 days)
Once everything is ready, the existing kitchen is carefully removed. This includes:
- Cabinets and countertops
- Flooring
- Appliances
- Possibly walls, depending on the layout changes
Tip: Prepare a temporary kitchen setup in another room to stay functional during this phase.
Structural Work and Rough-Ins (1–2 weeks)
This stage involves any:
- Wall framing or adjustments
- Plumbing, HVAC, and electrical updates
Tip: Ensure that any inspections required by local authorities are scheduled in advance to avoid downtime.

Installation (3–5 weeks)
This includes:
- Cabinetry installation (1–2 weeks)
- Countertop templating and installation (1–2 weeks after cabinets)
- Backsplash, flooring, lighting fixtures, and appliances
Tip: Expect some overlap in tasks, but build in buffer time for unexpected delays.
Final Touches and Cleanup (1 week)
Final inspections, paint touch-ups, hardware installation, and deep cleaning wrap up the project.
Total Timeline Summary
Phase | Estimated Duration |
Planning & Design | 2-6 weeks |
Ordering Materials | 2-8 weeks (overlapping) |
Demolition | 2-5 days |
Structural/Rough-Ins | 1-2 weeks |
Installation & Finishing | 2-5 weeks |
Total | 6-12 weeks (build) |
Top Planning Tips for a Smooth Renovation
- Set a Realistic Budget: Include a 10–20% contingency fund for unexpected costs.
- Communicate Clearly: Stay in regular contact with your contractor for updates and decisions.
- Plan for Life Without a Kitchen: Set up a mini kitchen with a microwave, kettle, and fridge.
- Be Flexible: Weather, inspections, or product delays can push schedules—build in buffer time.
Final Thoughts
While every kitchen renovation is unique, a well-planned project with a reliable team like Echelon Builds can keep stress to a minimum and results at their best. With the right prep, your dream kitchen will be well worth the wait. Contact us and let us help you with your kitchen renovation.